Kenexis is focusing on helping process companies to reduce costs.  SIS testing can have a large impact of costs of turnarounds.  When SIS testing prolongs turnarounds because it is performed at the end of the turaround after other work is completed.  The duration of time saved can be converted back into production time.  This can save one to three million dollars per day.  There are many methods and techniques that can be used to optimize SIS testing.  These methods include:

  • Moving tests outside the turnaround
  • Testing different subsystems at different intervals
  • Not testing non-essential equipment and functions

The following video presentation by Kenexis CEO Ed Marszal.  If after viewing the video you have any questions about the content that you would like to have answered, or if you would like to speak with Kenexis about assisting your organization regarding SIS testing optimization, please contact Kenexis by sending an e-mail to: [email protected] or calling us at +1 (614) 451-7031.